AUTHORIZATION TO CONTRACT WITH JOHNSON CONTROLS FOR THE ANNUAL CHILLER SERVICE AGREEMENT

Resolution Body

RESOLUTION NO. _____ - 2020

 

 AUTHORIZATION TO CONTRACT WITH JOHNSON CONTROLS FOR THE ANNUAL CHILLER SERVICE AGREEMENT

 Fiscal Impact: [ ] None [ X ] Budgeted Expenditure [ ] Not Budgeted

  Building Services operates and maintains four Trane Centrifugal chillers for the cooling of the facilities during the warm months of the year. (2) chillers at the Law Enforcement Center and (2) chillers at the West Square/Courthouse facility. Building Services has developed a practice of maintaining an annual service agreement on the chillers to help keep up with preventative maintenance on the chillers. The Buildings Services Facilities Director requested a three-year service contract proposal from both The Trane Company and Johnson Controls to provide the annual chiller service agreement. Johnson Controls was the only vendor to provide pricing for the three year service agreement at a cost of $45,430.00.  

NOW, THEREFORE, BE IT RESOLVED, by the Sauk County Board of Supervisors met in regular session, that the Building Services Facilities Director is hereby directed and authorized to contract with Johnson Controls to complete the annual chiller service agreement on the county’s four (4) Trane Centrifugal chillers at a cost of $45,430.00 for a three (3) year contract.

For consideration by the Sauk County Board of Supervisors on March 17, 2020.

 

Respectfully submitted,

Sauk County Property Committee

 

___________________________________                   ___________________________________

Scott Von Asten, chair                                        William Hambrecht

 

___________________________________                   ___________________________________

shane gibson                                                         carl gruber

 

                                                                    

JEAN BERLIN

 

 

FISCAL NOTE: Money for this maintenance contract is budgeted in the 2020 Building Services Contracted services budget.

 

MIS NOTE:   No MIS impact.

 

 

Chiller Services Pricing breakdown

 

Johnson Controls                    $45,430.00

 

Trane                                       Did not want to provide a bid